Play Strategy Appendix 3

Borough Council Investment Priorities

Parks Capital Programme 2006 to 2008

Summary

Project Responsibility Target deadline Budget allocation
Glossopdale Area
Brosscroft Play area, Hadfield Safety surfacingGroundwork Derby & Derbyshire Completed£3,000
Whitfield Recreation Ground play equipment & safety surfaceGroundwork Derby & DerbyshireNov 2006£13,500
Edale Close Play Area, Gamesley Multi play unitsGroundwork Derby & DerbyshireFeb 2007£20,000
Temple St Play Area, Padfield Multi Play unitGroundwork Derby & DerbyshireMarch 2007£14,000
Bankswood Park, Hadfield Multi play unitGroundwork Derby & DerbyshireDec 2006£6,000
(supplemented with £1,500
from Play Revenue)
Bankswood Park, Hadfield Path repairsGroundwork Derby & DerbyshireDec 2006£5,000
Manor Park, Glossop,Tree sculpture & viewing platformGroundwork Derby & Derbyshire Project at risk£10,000
Manor Park, Glossop Fencing Bowling GreenParksDec 06£5,500
Manor Park, Glossop boundary wallParksCompleted£1,800
Sexton Street, Tintwistle Bowling Green FencingParksDec 06£2,000
Roughfields, Hadfield BridgeParks Completed£1,980
Howard Park, Glossop Path repairsParks Completed£9,000
Howard Park, Glossop Drop down bollardParks Dec 06£1,000
Howard Park, Glossop Remove gulliesParks Dec 06£4,000
Howard Park, GlossopBase of statueGroundwork Derby & Derbyshire£3,000
Howard Park, Glossop BinsParksCompleted£3,000
Howard Park, GlossopFinger postsParksCompleted£1,500
Howard Park, GlossopBenches adapt to DDAParksMar 07£1,200
Howard Park, GlossopTree safety worksParksCompleted£2,250
Howard Park, GlossopWater courses (feasibility only)Groundwork Derby & DerbyshireApr 07£3,000
Central Area
Memorial Park, Whaley Bridge,Refurbishment ProgrammeGroundwork Derby & DerbyshireJun 07£88,000
Memorial Park, Whaley Bridge Welcome boardParksNov 06£2,850
Memorial Park, Whaley BridgeTree safety worksParksMar 07£2,250
Brookside, Chapel en le FrithPath repairsParksMar 07£1,000
Buxton Area
Green Lane Play Area, Buxton, Replace embankment slideGroundwork Derby & DerbyshireCompleted£5,600
Cote Heath Recreation Ground, Buxton Path repairsParksMar 07£1,500
Harpur Hill Play Area, BuxtonWall repairParksDec 06£1,500
Green Lane Play Area, BuxtonFull refurbishmentGroundwork Derby & DerbyshireApr 07£30,000
Ashwood Park BuxtonRefurbishment programmeGroundwork Derby & DerbyshireJun 07£58,000
Ashwood Park, BuxtonTree safety worksParksMar 07£1,500
Pavilion Gardens, BuxtonSurface to crazy golf & repair to wallGroundwork Derby & DerbyshireFeb 07£20,000
Pavilion Gardens, BuxtonSilt trapParksCompleted£600
Pavilion Gardens lights at Jordan’s walkParksNov 06£5,500
Temple Fields, Buxton,Car parkGroundwork Derby & DerbyshireCompleted£3,000
General Items
Bowling Greens grants to clubsParksApr 07£12,500
Groundwork SLA chargesParksJun 07£28,000
Floral display containersParksCompleted£3,200
General repairs to infrastructure Phase 1ParksCompleted£10,300
General repairs Phase 2GroundworkJun 07£30,000
Total budget allocation for Groundwork Projects£312,100
Total budget allocated as of 13th November 2006£416,030
Total budget available for general repairs£13,970 /£3,970
Spend allocation 2006-2007£203,500
Spend allocation 2007-2008£226,500
Grand Total £430,000
Playground

Appendices

Appendix 1: Summary of Audit of Borough Council and Parish Council owned Play Sites

Appendix 2: Parish Council Play Areas

Appendix 3: Borough Council Investment priorities

Appendix 4: Consultation and Involvement

Appendix 5: Action Plan

Appendix 6: Managing Risk in Play Provision - Full Statement

Investor in People and Positive about Disabled People logos