Fairfield Common A6 Roundabout

Temporary traffic lights in place on Fairfield Road from Monday 26 September (see the September Newsletter below for further details).


Galliford Try Traffic Management for roundabout works - overnight road closures

28 Nov to 3 Dec - 7pm till 6am from just north of Waterswallows Road junction to Batham Gate Road for work on the new roundabout.

New roundabout on the A6 at Fairfield

Working in partnership with Derbyshire County Council and Homes England, we are currently building a roundabout along the A6 at Fairfield Common. It is located at the very southern end of the Golf course.


Newsletter

Each month we will be publishing a newsletter about the Fairfield Common roundabout works. You can read the latest edition below.

Fairfield Roundabout Newsletter - November 2022 [825KB]
Fairfield Roundabout Newsletter - October 2022 [435KB]
Fairfield Roundabout Newsletter - September 2022 [420KB]
Fairfield Roundabout Newsletter - August 2022 [427KB]


Why do we need a roundabout there? 

The roundabout will provide access to land at Hogshaw and Waterswallows (Dale Lane) so that new homes can be built. These housing sites, and the proposal to build the roundabout, form part of the housing delivery policies within the adopted High Peak Local Plan.

Development of these housing sites is subject to separate delivery programmes and timescales. We have listened to recent feedback regarding site boundaries at Hogshaw and this is being considered as part of ongoing discussions with the developer. Any forthcoming scheme will have to be compliant with the current Local Plan.

There will be an opportunity for further public consultation on these developments through the statutory planning process once any application is received.

When will the work start?

The construction of the roundabout commenced on the 23 May and Galliford Try are working towards removing the traffic management system and completing the roundabout before the Christmas holiday.

Project Updates:

Utility Diversion: Openreach, Cadent and Electricity North West are undertaking diversion works during the period of the construction works.

Golf Club works: Some alterations have been made to the golf course around the 14th green and 15th  tee. These works are now complete.

Advanced tree felling: This work was completed at the end of February.

Below you can view a plan which identifies which trees have been removed. You can also view new tree planting proposals on the landscaping plan which shows replacement planting around the new roundabout.

Proposed Tree Removal and Re-Planting Plan [1MB]
Landscape Planting Plan [1MB]

How will the work affect me?

Two way traffic lights were installed on the 26th September. There is a full time operative who monitors traffic conditions and manually changes the traffic signals when required to keep the traffic moving.

We will update this page with information in advance and share this information on our Facebook and Twitter accounts so that you can plan your trip and allow extra time for travel.

You can also visit the Derbyshire County Council web site where you can view current and planned roadworks in your area..  

Useful Contacts:

Galliford Try site manager David Sims - mobile: 07821 651355

If you have queries about the project or its background then please address these to the County Council's Project Manager, Gary Thompson mobile: 07825 748 235 Email:gary.thompson@derbyshire.gov.uk or the Borough Council's Regeneration Team regeneration@highpeak.gov.uk.


These works are being funded by Homes England through their Housing Infrastructure Fund.